[LOGO] Davis and Associates, Inc.
Construction Management | General Contractors

AT&T First Floor Lobby and Café Renovation

Davis & Associates completed the general trades package associated with the renovation of the AT&T headquarters’ first floor lobby and working café’ located in downtown Indianapolis, IN.

This renovation involved remodeling of finishes, revitalizing spaces, and modernizing four entrances to the building.  It is also converted over 4,200 s.f. of outdated office space into a state of the art working café.

The general trades package included: general conditions, rough carpentry, doors, frames and hardware, automated doors, coatings, and finishes.

DR8PVdpE7nuJSZIFuqVEDP1EGZ3gQBG3KHI9opuoaWg,hsZc2-OnIX7NFmSrHAaA2PP4GFxZd5fYqCn83TcmbcQ,OolESonb3rDv140wXVBcdyybcJWM0OhlDliNxM3dJ5o,rIIx7YcSOnvgNPWbMzZaxQzcdK_V7Vf2a_PizQFFD4o,WWLy0yvda0NpUvf7VJxKVNHKPHPhd79ap860iNV5fgc,P0-1yDRGdQkCZbWWN40RhLHDu5gRawNT2IH6s4D9ZYppQ1k,0mYw3iXVASwXaBRzev-lggGHLW6RtldIBN1AYLk0L0E,MfUhBmr0bKEUT89r3kPynP9xE1sGyi6Jxyjg0Eg3OIQ,ZQACUVdZIek9dnovonVP57uwTKeKkkROgNMVoMxTRUc,tb7V2hanCeyBvFnY0Wj0e8FpylJV2VZMQw-GcyNKLtI

CONRAC Low-Voltage GAP

Davis & Associates managed the installation of infrastructure and equipment to integrate existing stand-alone low voltage systems at various CONRAC facilities into existing Airport-wide systems.

The Consolidated Car Rental (CONRAC) Facility was one of the many projects included in Atlanta, Georgia’s Hartsfield-Jackson Airport Capitol Improvement Program.

The CONRAC houses all Airport car rental companies and their operations, including customer service, administrative and maintenance offices. By consolidating the various rental car companies, the Airport hopes to improve the traffic flow around the passenger terminal.

 

Citizens-ONS Structural Roofing Repairs at Belmont & Southport AWT Plants

Last deck placement - southportOK 2014 Citizens ONS Structural Roofing 2

The project included removal and replacement of 1,053 cys of existing concrete topping slabs, new thermoplastic sheet waterproofing, removal of existing precast panel siding and roofing and installation of new metal siding and thermoplastic roofing on two pump buildings, removal and replacement of existing metal fascia panels and plaster soffits on two control buildings, at two active advance water treatment plants.